Ho Chi Minh City will hold a press conference on the mistakes in Thu Thiem next week

Information Chairman of the City People’s Committee will report the results of inspection conclusions to the Standing Party Committee, then urgently organize a press conference on the violations in Thu Thiem.

In the morning of June 27, Chairman of Ho Chi Minh City People’s Committee Nguyen Thanh Phong said that the city has not received official inspection conclusions on the state management and implementation of laws in planning, construction and land management. with Thu Thiem New Urban Area.

Mr. Phong said he only knew about newspapers and the Internet. The City People’s Committee will make a plan to carry out the inspection conclusion and take the initiative in implementing it immediately upon receiving the official document.

“Next Monday, I will report to the Standing Party Committee. After that, a press conference will be held ”, Mr. Phong informed.

 

Chairman of City People’s Committee Nguyen Thanh Phong

Responding to the question of the conclusion of the inspection not to mention the complaints of the people, Mr. Phong said this issue was stated in the announcement concluding 1483 in September 2018. In recent years, the City People’s Committee has actively implemented many jobs according to this conclusion.

On the sidelines of the Congress of the Ho Chi Minh City Fatherland Front Committee took place in the morning, the reporter asked Mr. Le Thanh Hai, former City Party Committee Secretary, about the violations of the City in the District. Thu Thiem new urban area that the Government Inspector has just stated in the inspection conclusion. However, Mr. Hai refused to answer.

Meanwhile, Ms. Nguyen Thi Quyet Tam, former Chairman of the People’s Council of Ho Chi Minh City, said that she also had access to the inspection conclusion of Thu Thiem New Urban Area on the network but not yet received the paper. She said that she would carefully review the contents of this conclusion and exchange later.

A corner of Thu Thiem urban area

On September 7, 2018, the Government Inspectorate concluded the HCM City People’s Committee’s decision to recover land for an area of ​​4.3 hectares in Quarter 1, Binh An Ward to implement some projects at Thu Thiem is not enough legal basis, not in accordance with the plan approved by the Prime Minister. The City People’s Committee needs to review cases of complaints, especially cases in the 4.3 ha area.

On June 26, Government Inspectorate issued conclusions on inspection of State management and implementation of laws in planning, construction and land management for Thu Thiem New Urban Area, District 2, Ho Chi Minh City. . The Government Inspectorate pointed out a series of violations of the City People’s Committee and the names of many departments and agencies concerned.

The main violations pointed out by the Government Inspectorate include: All land fund in Thu Thiem New Urban Area is 221.68 ha created by the State budget, Ho Chi Minh City People’s Committee has mainly used to Reciprocal payments for BT projects are designated investors without bidding.

This violates the regulations on bidding and land use management. With BT project of 4 main roads, Ho Chi Minh City appointed Dai Quang Minh Joint Stock Company to be an investor when no proposal has been made and evaluation of standards of experience, no assessment of financial capacity … is wrong regulation.

The City People’s Committee approved the project, approved a total investment of more than VND 12,000 billion for the project of 4 main roads in Thu Thiem New Urban Area without clarifying the opinions of relevant departments and agencies. Through inspection, the authorities discovered a number of improper approvals with a total value of over VND 1,500 billion.

From the series of mistakes pointed out, the General Inspector of the Government proposed to the Prime Minister to direct the ministries and the People’s Committee of Ho Chi Minh City to correct the management and policy mechanisms.

Ho Chi Minh City People’s Committee had to withdraw and return VND 26,300 billion immediately, improperly advanced from the State budget to invest in Thu Thiem New Urban Area by September 30, 2018. In addition, the City soon has a solution to mobilize legal capital sources to repay the loans that banks have invested in Thu Thiem New Urban Area which is more than 4,200 billion.